Replacing water mains – Uxbridge

June 2017 – January 2018

 

We are replacing 1.8km of water mains in Uxbridge (Frays River). To ensure we can continue to provide our customers with good quality water and reduce the number of bursts and leaks in the area. Some pipes in the area can be up to 53 years old! The work will help reduce the number of times we dig up the road causing disruption to your community.

The works started on 1 Jun 2017 and we aim to finish in early January 2018.

We will be working in other roads off the high street but the high street will be open.

During the Christmas period, the local authority may put restrictions in place to prevent us from working, but we will re-start in January.

 

Where we are working

The following streets may be affected:

  • Alley Way, UB8

  • Baker's Road, UB8 1RG

  • Bakers Yard, UB8 1GG

  • Bennetts Yard, UB8 1AN

  • Chippendale Alley, UB8

  • High Street, UB8 1GA

  • Orchard Place, UB8 3TQ

  • Vine Street, UB8 2AN

  • Windsor Street, UB8 1AB

 

Please see below for the diversion route that will be in place.

 

 

 

The map below shows the streets that where we will be working

 

Local residents

If you will be affected by this works, we will send a letter and leaflet two weeks prior to when we start work on the street.

Monday – Friday : 8am - 6pm

Saturday or Sunday: We may occasionally work on an agreed basis