Serving parts of North West London and the Home Counties.

Lead pipe replacement

Squires Lane, Barnet

 

We are spending £25 million on a program to replace lead pipework across our network between 2015 and 2020. As part of this, we have planned works to replace lead pipework in Squires Lane, Finchley from 29 July 2019.

We are carrying out these works in your area, to make sure we can continue to provide a reliable and high-quality supply of water to your community for many years to come.

 

Road closures & diversions

We have been working closely with Barnet Council and have agreed to carry out this work during the school summer holidays, to reduce disruption to you. However, work on Squires Lane will require temporary traffic lights and/or road closures to be put in place from 29 July 2019, for a 6-week period. To see a map of these works and receive regular updates please click here.

 

When will this work start and finish?

This work is due to start on Monday 29 July and will continue for six weeks.

 

Where is this work taking place?

Week 1 & 2      

Squires Lane, section from junction with High Road to junction with Glebe Road and Clifton Road and,

Squires Lane, section from junction with Long Lane to junction with Etchingham Park Road

Week 3

Squires Lane, section from junction with Etchingham Park Road to junction with Glebe Road and Clifton Road

Week 4 - 6

Squires Lane, section from Long Lane to junction with Balfour Terrace

 

More information

If your water supply or access to your property is affected by these works, you will have already received a letter from us with more advice. You can leave us feedback at any time here or if you have any questions you can contact us on 0345 357 2403.