Essential Production Works Info - Dunstable - LU6
Monday 10th February 2025

Essential Production works in Dunstable
What we’re doing
We are carrying out essential Production works from Monday 10th February 2025 to Friday 14th February 2025. Customers within these zones may experience intermittent periods of lower pressure than usual.
To find out if your street may be affected, please click here
We added this message at 08:00 on Thursday 14th February 2025 and we'll remove it after 08:00 on Saturday 15th February 2025
What's happened so far?
Friday 14th February 2025
(08:00) Testing of the new boosters continues today, throughout the day.
Thursday 13th February 2025
(08:00) New boosters on site are being tested today, throughout the day.
Wednesday 12th February 2025
(08:00) Further testing and proving is taking place today throughout the day.
Tuesday 11th February 2025
(08:00) New booster are being installed and will be tested over night to ensure reliability.
Monday 10th February 2025
(08:00) Equipment pre checks and offline testing are taking place today throughout the day.